Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
METHUEN- ADA RETROFITS AT VARIOUS LOCATIONS
The work to be done under this contract consists of pedestrian curb ramp construction, reconstruction, repairs, and upgrades at the following locations along Merrimack Street (Route 110) in Methuen: Merrimack Street (Route 110) at its intersection with Myona Street, Ayer Street, West Ayer Street, Riverdale Street, Alton Road, Golf Avenue, Booth Road, Comet Road, Bradley Avenue, Derry Road, Erie Road, Frye Road, Meriline Avenue, Sorrento Avenue, Messina Avenue, Wingate Avenue, Thornton Avenue, Taft Avenue, Walton Avenue, Wallace Street, Pitman Street, Ames Street, Arcadia Street, Albermarle Street, Newbury Avenue, Sunnyside Street, Ford Street, Randolph Avenue, Farley Street, Simone Street, Campbell Street, Pleasant Valley Street, Ferry Road, Village Lane, Renfrew Street, Whittier Street, Brookdale Avenue, Webster Avenue, and Addison Avenue. Work shall include, but not be limited to: construction or reconstruction of cement concrete pedestrian curb ramps, construction or reconstruction of cement concrete and hot mix asphalt sidewalks and driveways, drainage alterations as needed, removing and resetting of curb and transition curb as required, and repairing of roadway cuts required to perform work including full depth construction and fine milling with HMA overlay. The work also consists of modifications to existing traffic signals.
Location:
  • Town of Methuen
  • Construction Begins: Summer 2024
    Resident Engineer: Pamela Mamacos
    Construction Bid Price: $2,731,621.00
    District: District 4

    Contracts (2) Progress
    # 126425 -- Construction Contract
    ADA Retrofits at Various Locations 25% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/26/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2019
    Project Need Form PNF Approved 03/11/2019
    Project Initiation Form PIF Entered 05/07/2019
    Project Initiation Form PIF Approved 03/21/2019
    Project Initiation Form PRC Submitted 10/09/2019
    Project Review Committee PRC Approved 10/15/2019
    Project Status Advertised 06/22/2024
    Project Management
    100% Design 100% Package Received 12/18/2023
    25% Design 25% Package Received 12/06/2022
    75% Design 75% Package Received 12/06/2022
    75% Design 75% Package Comments to DE 01/06/2023
    Final Design PS&E Received 12/18/2023
    Final Design PS&E Received - Resub 1 04/12/2024
    Final Design PS&E Received - Resub 2 04/30/2024