Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- ADA RETROFITS AT VARIOUS LOCATIONS
The work to be done under this Contract consists of furnishing all required labor, materials and equipment required for the reconstruction of pedestrian facilities located within the designated project limits as shown in the Contract Drawings at over 60 locations in Cohasset, Duxbury, Fall River, Hingham, Kingston, Marion, Plymouth, Rockland and Swansea. The project includes removal of HMA and Portland cement concrete sidewalks and pedestrian curb ramps and installation of concrete sidewalks and pedestrian curb ramps, granite curb, thermoplastic crosswalks, pavement markings, utility adjustments, drainage adjustments, signing, and other incidental items included in the Contract Documents. The scope of work also includes the maintenance and protection of traffic during construction, maintenance of vehicular and pedestrian access to abutting properties, and maintenance of uninterrupted utility service.
Location:
Construction Begins: Winter 2024/2025
Resident Engineer: Matthew Blackwell
Construction Bid Price: $2,622,295.56
District: District 5
Current Status: The contractor has finished the new pedestrian curb ramps along Route 6 in Marion and has installed the new granite curb along N. Main St in Fall River. He plans to place the concrete ramps and HMA sidewalk in Fall River by 9/12/25. He milled the roadway along Route 3A at Pond St in Cohasset and plans to pave the area within the next 2 weeks. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 09/02/2025)

Contracts (3) Progress
# 115769 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final
# 128748 -- Construction Contract
ADA Retrofits at Various Locations 44% Complete
# 77866 -- Design -- Hwy Eng Open End
Master Service Agreement for statewide design and review services. Final

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/23/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2019
    Project Need Form PNF Approved 03/11/2019
    Project Initiation Form PIF Entered 05/07/2019
    Project Initiation Form PIF Approved 03/21/2019
    Project Initiation Form PRC Submitted 10/09/2019
    Project Review Committee PRC Approved 10/15/2019
    Project Status Advertised 11/16/2024
    Project Management
    100% Design 100% Package Received 12/13/2023
    100% Design 100% Package Comments to DE 01/24/2024
    25% Design 25% Package Received 12/16/2022
    25% Design Design Public Hearing 08/23/2023
    75% Design 75% Package Received 12/16/2022
    75% Design 75% Package Comments to DE 01/19/2022
    Final Design PS&E Received 08/07/2024
    Final Design PS&E Received - Resub 1 10/23/2024
    Final Design PS&E Received - Resub 2 11/15/2024
    Final Design PS&E Received - Resub 3 11/18/2024