Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST STOCKBRIDGE- STOCKBRIDGE- INTERSTATE MAINTENANCE AND RELATED WORK ON I-90
The proposed project is resurfacing and related work with bridge shielding for occupant protection at 9 bridges and concrete repair on 6 bridge piers within the project limits. This project starts at the New York/Massachusetts state line on I90 and proceeds for a total of 7.8 miles to the Stockbridge/Lee town line. This Interstate Project includes the towns of West Stockbridge and Stockbridge. Proposed work will include milling, subbase patching where required, hot mix asphalt overlay, pavement marking, guardrail upgrades, drainage repair and upgrade, installing bridge shielding for occupant protection, and other incidental work. It will encompass the full width of the road. All on/off ramps and access roads will be included in the resurfacing project. Bridge work consist of concrete pier repairs, protection of the piers with fiber reinforcement polymer (FRP), and related work performed on the bridges designated.
Location:
  • Town of Stockbridge
  • Town of West Stockbridge
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Zahid Pervaiz
    Construction Bid Price: $24,361,298.89
    District: District 1

    Contracts (1) Progress
    # 124762 -- Construction Contract
    Interstate Maintenance and Related Work on I-90

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/12/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/13/2019
    Project Need Form PNF Approved 05/13/2019
    Project Initiation Form PIF Entered 05/13/2019
    Project Initiation Form PIF Approved 05/13/2019
    Project Initiation Form PRC Submitted 05/13/2019
    Project Review Committee PRC Approved 05/16/2019
    Project Status Advertised 12/02/2023
    Project Management
    100% Design 100% Package Received 09/29/2022
    100% Design 100% Package Comments to DE 10/19/2022
    25% Design 25% Package Received 05/12/2022
    75% Design 75% Package Received 05/12/2022
    75% Design 75% Package Comments to DE 06/13/2022
    Final Design PS&E Received 01/18/2023
    Final Design PS&E Received - Resub 1 09/19/2023