Project Description:
WESTON- INTERSTATE MAINTENANCE AND RELATED WORK ON I-90
This project consists of resurfacing I-90 Eastbound from MM 122.328 to MM 124.463 and Westbound from MM 14.819 to MM 16.95 for a total distance of 4.22 miles.
Location:
  • Town of Weston
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $6,098,400.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/14/2019
    Project Need Form PNF Approved 05/14/2019
    Project Initiation Form PIF Entered 05/14/2019
    Project Initiation Form PIF Approved 05/14/2019
    Project Initiation Form PRC Submitted 05/14/2019
    Project Review Committee PRC Approved 05/17/2019