Project 609493
(Click here for a glossary of terms)
Project Description:
SWANSEA- BRIDGE PRESERVATION ON S-35-014 (3WP)
Location:
Town of Swansea
Construction Begins:
Spring 2020
Resident Engineer:
Rajat Gogoi
Construction Bid Price:
$2,214,560.00
District:
District 5
Contracts
(1)
Progress
# 110727 -- Construction Contract
Bridge Cleaning, Painting and Related Work (Including Structural Steel Repairs) Br. No. S-35-014 Route 6 over Interstate 195.
Completed
Bridges
S35014
details...
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
05/28/2020
Contract Information
Project Designer:
In-House Boston
Funding Source:
Non Federal Aid
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2025 - 2029
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
05/29/2019
Project Initiation Form
PIF Entered
05/29/2019
Project Initiation Form
PRC Submitted
05/29/2019
Project Review Committee
PRC Approved
06/06/2019
Project Status
Advertised
02/01/2020
Project Management
100% Design
100% Package Received
12/24/2019
100% Design
100% Package Comments to DE
01/09/2020
75% Design
75% Package Received
11/18/2019
75% Design
75% Package Comments to DE
12/11/2019
Final Design
PS&E Received
01/16/2020
Final Design
PS&E to FAPRO
01/27/2020