BECKET- LEDGE REMOVAL ALONG ROUTE 8, BETWEEN MM 28.002 AND MM 27.998
Throughout the District, ledge out-croppings and exposed rock faces are adjacent to State Highway at various locations. Some of these areas were created when the highways were originally built, reconstructed or widened; or when natural events, such as Tropical Storm Irene, exposed natural rock slopes to additional weathering and erosion. Many of these locations pose a potential safety hazard from falling rock or slope failure, which could injure highway users or shut down some sections of State Highway for an extended time. Highway closures at many of these locations would result in lengthy detours, affecting regional commuting and commerce. This proposed contract would design site-specific improvements to address safety issues related to exposed or falling rock at these locations.
Location:
  • Town of Becket
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $2,693,856.85
    Estimated Total Federal Participating Construction Cost: $2,950,417.19
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 25% Package Received (as of 08/05/2024 )

    Contracts (1) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: BECKET
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation (PROTECT)
    Federal Cost: $2,080,000.00
    State Cost: $520,000.00
    Total Cost: $2,600,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/26/2019
    Project Initiation Form PIF Entered 06/26/2019
    Project Initiation Form PRC Submitted 06/26/2019
    Project Review Committee PRC Approved 07/15/2019
    Project Management
    25% Design 25% Package Received 08/05/2024