Project Description:
DRACUT- IMPROVEMENTS AT GEORGE ENGLESBY ELEMENTARY SCHOOL (SRTS)
The proposed improvements primarily consist of eliminating sidewalk gaps along Lakeview Avenue from Old Road to Primrose Hill Road, as well as along Turgeon Avenue and New Boston Road between Lakeview and Hurley. Other project elements include new crosswalks and one pedestrian signal. The total project length along Lakeview Ave is approximately 1.4 miles. The total project length along Turgeon Avenue is approximately .06 miles. The total project length along Old Boston Road is approximately .03 miles. The total length of sidewalk gaps is approximately 4,000 feet. New crosswalks are proposed at Turgeon/Hurley, Primrose Hill/Lakeview, Saint Paul/Lakeview, Saint James/Lakeview, Vinal/Lakeview, Martin Terrace/Lakeview, Hypine/Lakeview, and Pearl/Lakeview. A pedestrian signal head is proposed at Tennis Plaza/Lakeview. Pedestrian crossing signs are proposed at Frederick/Lakeview.
Location:
  • Town of Dracut
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $2,448,000.00
    Estimated Total Federal Participating Construction Cost: $2,643,360.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (2) Progress
    # 115759 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 86787 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: DRACUT
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Total cost: $1,115,100; YOE: $1,159,704; Funding: TAP TEC: 8 out of 18;
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $927,763.20
    State Cost: $231,940.80
    Total Cost: $1,159,704.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/19/2019
    Project Need Form PNF Approved 07/10/2019
    Project Initiation Form PIF Entered 07/19/2019
    Project Initiation Form PIF Approved 07/19/2019
    Project Initiation Form PRC Submitted 07/29/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management