Project Description:
NORTHAMPTON- BRIDGE STREET ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
Location:
  • City of Northampton
  • Construction Begins: Autumn 2022
    Resident Engineer: Peng Xu
    Construction Bid Price: $821,471.00
    District: District 2

    Contracts (1) Progress
    # 119243 -- Construction Contract
    Sidewalk Reconstruction and Related Work along Sections of Bridge (Route 9), Parsons and Hawley Streets (Safe Routes to School - Bridge Street Elementary School)

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/22/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/22/2019
    Project Need Form PNF Approved 06/21/2019
    Project Initiation Form PIF Entered 07/22/2019
    Project Initiation Form PIF Approved 07/22/2019
    Project Initiation Form PRC Submitted 07/22/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Status Advertised 07/23/2022
    Project Management
    100% Design 100% Package Received 08/20/2021
    25% Design 25% Package Received 11/06/2020
    25% Design Design Public Hearing 06/02/2021
    75% Design 75% Package Received 08/20/2021
    Final Design PS&E Received 11/12/2021
    Final Design PS&E to FAPRO 07/11/2022
    Final Design PS&E Received - Resub 1 02/11/2022
    Final Design PS&E Received - Resub 2 03/11/2022
    Final Design PS&E Received - Resub 3 06/14/2022