BURLINGTON- IMPROVEMENTS AT I-95 (ROUTE 128)/ROUTE 3 INTERCHANGE
The proposed work consists of improving traffic operations and safety at Interstate 95 and Route 3 Interchange.
Location:
  • Town of Burlington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: David Shedd
    Estimated Total Contract Cost: $5,535,421.85
    Estimated Total Federal Participating Construction Cost: $6,020,497.10
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Received (as of 04/24/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BURLINGTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $3,498,560 (NHPP)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $2,798,848.00
    State Cost: $699,712.00
    Total Cost: $3,498,560.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/24/2019
    Project Need Form PNF Approved 07/17/2019
    Project Initiation Form PIF Entered 07/24/2019
    Project Initiation Form PIF Approved 07/24/2019
    Project Initiation Form PRC Submitted 07/29/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management
    25% Design 25% Package Received 12/01/2023
    25% Design 25% Package Comments to DE 01/10/2024
    25% Design Design Public Hearing 04/02/2024
    75% Design 75% Package Received 04/24/2024