Project Description:
FAIRHAVEN- LEROY WOOD ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
Location:
  • Town of Fairhaven
  • Design Responsibility: Consultant
    Construction Begins: Summer 2024
    Project Manager: Linda Walsh
    Estimated Total Contract Cost: $1,693,176.60
    Estimated Total Federal Participating Construction Cost: $799,035.00
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received - Resub 2 (as of 06/06/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: FAIRHAVEN
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,553,368.80
    State Cost: $388,342.20
    Total Cost: $1,941,711.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/26/2019
    Project Need Form PNF Approved 07/15/2019
    Project Initiation Form PIF Entered 07/26/2019
    Project Initiation Form PIF Approved 07/26/2019
    Project Initiation Form PRC Submitted 07/26/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management
    25% Design 25% Package Received 04/04/2022
    25% Design 25% Package Received - Resub 1 01/19/2022
    25% Design 25% Package Received - Resub 1 04/04/2022
    25% Design 25% Package Received - Resub 2 06/06/2022
    Consultant Contract Process Scope to DE 09/10/2020
    Consultant Contract Process NTP Issued 09/10/2020