Project Description:
FAIRHAVEN- LEROY WOOD ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
Work on this project consists of sidewalk installation, bicycle lanes, ADA compliant curb ramps and associated work on Sconticut Neck Road to improve accessibility for bicyclists and pedestrians to the Leroy Wood School from the abutting neighborhoods and the Phoenix Rail Trail.
Location:
  • Town of Fairhaven
  • Construction Begins: Spring 2024
    Resident Engineer: Neal Noversa
    Construction Bid Price: $1,855,465.00
    District: District 5
    Current Status: Third party utility force account work is continuing with overhead cable transfers from existing poles to newly set poles along Sconticut Neck Rd. Contractor plans to remobilize fully to the project site once utility poles are removed from sidewalk areas. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 06/23/2025)

    Contracts (1) Progress
    # 125645 -- Construction Contract
    Leroy Wood Elementary School Improvements (SRTS) 63% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/17/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Third party utility force account work is continuing with overhead cable transfers from existing poles to newly set poles along Sconticut Neck Rd. Contractor plans to remobilize fully to the project site once utility poles are removed from sidewalk areas. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/26/2019
    Project Need Form PNF Approved 07/15/2019
    Project Initiation Form PIF Entered 07/26/2019
    Project Initiation Form PIF Approved 07/26/2019
    Project Initiation Form PRC Submitted 07/26/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Status Advertised 03/30/2024
    Project Management
    100% Design 100% Package Received 10/23/2023
    25% Design 25% Package Received 04/04/2022
    25% Design 25% Package Received 12/23/2022
    25% Design 25% Package Received - Resub 1 01/19/2022
    25% Design 25% Package Received - Resub 1 04/04/2022
    25% Design 25% Package Received - Resub 2 06/06/2022
    25% Design Design Public Hearing 09/15/2022
    75% Design 75% Package Received 12/28/2022
    Final Design PS&E Received 01/16/2024
    Final Design PS&E to FAPRO 03/18/2024
    Consultant Contract Process Scope to DE 09/10/2020
    Consultant Contract Process NTP Issued 09/10/2020