BROCKTON- ABINGTON- PEDESTRIAN AND BICYCLE IMPROVEMENTS ON ROUTE 123
The purpose of this project is to provide safety improvements on Centre Street and Brockton Avenue (Route 123) from a point approximately 350 feet easterly of the intersection of Route 123 at Lyman and Cary Street, extending easterly into Abington, ending at Ashland Street, a length of approximately 2.3 miles. The project consists of corridor safety and operational improvements for all modes of travel and will include new ADA compliant sidewalks, buffered bicycle lanes, roadway pavement reconstruction, drainage improvements, improved traffic operations and safety, new signage and pavement markings.
Location:
  • Town of Abington
  • City of Brockton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Jonathan E Freeman
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Planned Federal FY: 2029
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: ABINGTON
    BROCKTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Total cost $29,519,606; AC 2029, 2040; YOE 2029, TEC Score: 53; Funding Source: NHPP; Pre-25%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $12,049,567.20
    State Cost: $3,012,391.80
    Total Cost: $15,061,959.00

    Planned Federal FY: 2030
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: ABINGTON
    BROCKTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Total cost $29,519,606; AC 2029, 2040; YOE 2029, TEC Score: 53; Funding Source: NHPP; Pre-25%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $14,400,000.00
    State Cost: $3,600,000.00
    Total Cost: $18,000,000.00