Project Description:
GRAFTON- MILLBURY STREET IMPROVEMENTS (SRTS)
The Millbury Street Safe Routes to School Project will install over 4200 linear feet of sidewalk along Millbury Street and 850 linear feet of sidewalk along Crosby Road to connect neighborhoods for Sean Mikael Way Oak Ridge Lane Fitzpatrick Road Blanchard Road and Cortland Way. Millbury Street has no pedestrian accommodations to connect Millbury Street School with the surrounding neighborhoods. This project will address pedestrian safety issues through the construction of five 5 foot wide sidewalks, install ADA compliant crossings at intersections within the project area, and install pedestrian warning and crossing equipment to facilitate safe access to the Millbury Street School from adjacent neighborhoods.
Location:
  • Town of Grafton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2024
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $3,341,407.54
    Estimated Total Federal Participating Construction Cost: $3,177,661.41
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received (as of 02/21/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: GRAFTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $1,931,230, Design Status = 100%
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,544,984.00
    State Cost: $386,246.00
    Total Cost: $1,931,230.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/29/2019
    Project Need Form PNF Approved 07/01/2019
    Project Initiation Form PIF Entered 07/29/2019
    Project Initiation Form PIF Approved 07/29/2019
    Project Initiation Form PRC Submitted 07/30/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management
    100% Design 100% Package Received 01/28/2023
    100% Design 100% Package Comments to DE 04/13/2023
    25% Design 25% Package Received 02/22/2022
    25% Design 25% Package Comments to DE 04/26/2022
    25% Design Design Public Hearing 09/20/2022
    75% Design 75% Package Received 01/28/2023
    Final Design PS&E Received 02/21/2024