Project Description:
LEOMINSTER- VISCOLOID AVENUE IMPROVEMENTS (SRTS)
The proposed improvements include, pedestrian traffic signals, sidewalks with granite curbing, ADA Accessible ramps, crosswalks and signage which will provide better pedestrian access to the Frances Drake School and the State Pool complex. The proposed sidewalks will infill and/or replace areas along Viscoloid Avenue with no sidewalks and poor sidewalks which will in turn provide access from Route 117 to Mechanic Street.
Location:
  • City of Leominster
  • Construction Begins: Autumn 2022
    Resident Engineer: Carmen Ramirez
    Construction Bid Price: $2,550,647.89
    District: District 3

    Contracts (1) Progress
    # 119986 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on Viscoloid Avenue (Safe Routes to School – Frances Drake Elementary School) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/12/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/29/2019
    Project Need Form PNF Approved 07/12/2019
    Project Initiation Form PIF Entered 07/29/2019
    Project Initiation Form PIF Approved 07/29/2019
    Project Initiation Form PRC Submitted 07/30/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Status Advertised 08/20/2022
    Project Management
    100% Design 100% Package Received 01/20/2022
    100% Design 100% Package Comments to DE 02/23/2022
    25% Design 25% Package Received 02/18/2021
    25% Design 25% Package Comments to DE 04/21/2021
    25% Design Design Public Hearing 10/07/2021
    75% Design 75% Package Received 02/18/2021
    75% Design 75% Package Comments to DE 04/21/2021
    75% Design 75% Package Received - Resub 1 10/20/2021
    Final Design PS&E Received 05/03/2022
    Final Design PS&E Received - Resub 1 05/27/2022
    Final Design PS&E Received - Resub 2 06/29/2022