Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ARLINGTON- STRATTON SCHOOL IMPROVEMENTS (SRTS)
Provide fully accessible safe walking route with safe roadway crossings for pedestrians and children walking to Stratton Elementary School in Arlington on Hemlock Street between Pine Street and Dickson Avenue; and Dickson Avenue between Hemlock Street and Pheasant Avenue. Install new sidewalk on the east side of Hemlock Street between Lansdowne Road and Yerxa Road. Install new sidewalk on the southwest/northwest sides of the Hemlock Street and Dickson Avenue intersection and on the northwest side of Dickson Avenue to Pheasant Avenue. Install new or upgrade curb ramps within project limits. Repair or replace existing sidewalks on Hemlock Street from Dickson Avenue to Pine Street. Replace or reset existing granite curbing within project limits. Total amount of new and replaced sidewalk (standard 5' wide) amounts to approximately 2,434 linear feet. Narrow and modify roadway intersections with curb extensions to slow vehicles and reduce pedestrian crossing distances along Hemlock Street at the following intersections: Pine Street, Yerxa Road, and Dickson Avenue; and at Dickson Avenue and Pheasant Avenue. Provide safe and accessible pedestrian crossings across Hemlock Street at Yerxa Road and at Hemlock Street and Dickson Avenue, and at Dickson Avenue and Pheasant Avenue. Install all necessary signage and pavement markings. Install new pedestrian-activated signal (Rectangular Rapid Flashing Beacon) at Hemlock Street and Yerxa Road crosswalk.
Location:
  • Town of Arlington
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $2,058,883.65
    Estimated Total Federal Participating Construction Cost: $2,308,174.79
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: PS&E Received (as of 11/01/2024 )

    Contracts (1) Progress
    # 86787 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: ARLINGTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,706,938.40
    State Cost: $426,734.60
    Total Cost: $2,133,673.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/29/2019
    Project Need Form PNF Approved 07/16/2019
    Project Initiation Form PIF Entered 07/29/2019
    Project Initiation Form PIF Approved 07/29/2019
    Project Initiation Form PRC Submitted 07/29/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management
    100% Design 100% Package Received 04/25/2024
    25% Design 25% Package Received 01/03/2022
    25% Design 25% Package Comments to DE 04/20/2022
    25% Design Design Public Hearing 01/12/2023
    75% Design 75% Package Received 06/30/2023
    75% Design 75% Package Comments to DE 09/29/2023
    75% Design 75% Package Received - Resub 1 01/26/2024
    Final Design PS&E Received 11/01/2024