Project Description:
CHELSEA- TARGETED SAFETY IMPROVEMENTS AND RELATED WORK ON BROADWAY, FROM WILLIAMS STREET TO CITY HALL AVENUE
The project will include corridor wide safety improvements targeted at reducing crashes for pedestrians, bicycles and vehicles. Standard safety countermeasures such as improved signage, lighting, traffic calming streetscape elements, curb extensions, signal upgrades (where applicable) and other countermeasures identified in the Road Safety Audit. In addition, it is expected that the corridor's pavement, sidewalks and bus transit amenities will need to be improved or replaced; however, at this time, not enough baseline data or survey has been gathered to fully assess the condition of those assets. Further evaluation of the pavement treatment and extent of sidewalk reconstruction will be conducted during initial project development. The cross-section elements will be developed during initial project development building on the planning work that has already been conducted by the City of Chelsea.
Location:
  • City of Chelsea
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Lawrence Cash
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CHELSEA
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $9,723,791.70
    State Cost: $1,080,421.30
    Total Cost: $10,804,213.00