Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WESTFIELD- PEDESTRIAN AND BICYCLE IMPROVEMENTS ON MAIN STREET (ROUTE 20)
Roadway was identified through the Pedestrian and Bicycle Plans for high potential for Walkable Trips and Everyday Biking with the aim to increase and improve for people walking biking and taking transit. The proposed project consists of adding a sidewalk on the north side of US 20 between Noble Street and Delmont Avenue in the City of Westfield, improving transit accommodations, and reconstructing curb lines and wheelchair ramps at the intersections with Meadow Street and Mainline Drive. Protected bike lanes are proposed between Mainline Drive and Delmont Avenue. The proposed roadway work includes milling and overlaying the existing roadway, and replacing traffic signal equipment to accommodate pedestrian crosswalks on all approaches to the four signalized project intersections.
Location:
  • City of Westfield
  • Design Responsibility: Consultant
    Project Manager: Stephanie Upson
    Estimated Total Contract Cost: $2,987,720.58
    Estimated Total Federal Participating Construction Cost: $3,305,810.99
    District: District 2
    Current Status: 25% Package Received (as of 05/26/2021 )

    Contracts (1) Progress
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/30/2019
    Project Need Form PNF Approved 07/30/2019
    Project Initiation Form PIF Entered 07/30/2019
    Project Initiation Form PIF Approved 07/30/2019
    Project Initiation Form PRC Submitted 08/06/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management
    25% Design 25% Package Received 05/26/2021