Project Description:
BOURNE- ROTARY IMPROVEMENTS
Work on this project consists of improving the traffic operations through restriping the rotary to 2 lanes and adding a channelized right turn lane from Route 28 northbound to Sandwich Road eastbound.
Location:
  • Town of Bourne
  • Construction Begins: Autumn 2023
    Resident Engineer: Neal Noversa
    Construction Bid Price: $1,769,622.60
    District: District 5
    Current Status: Sub-contractor has been performing ongoing proposed sloped granite edging and vertical curb installation along rotary approaches and splitter islands. Contractor has excavated down to subgrade for proposed truck apron at Sandwich Rd. approach. Backfilling and grading behind curb/edging areas with ordinary borrow and loam is currently ongoing. Existing flashing warning beacons have been removed and discarded form rotary approach splitter islands.. Scheduled work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 04/04/2024)

    Contracts (1) Progress
    # 123878 -- Construction Contract
    Rotary Improvements 56% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/09/2023
    Contract Information
    Project Designer:
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/13/2019
    Project Need Form PNF Approved 08/06/2019
    Project Initiation Form PIF Entered 08/13/2019
    Project Initiation Form PIF Entered 09/29/2020
    Project Initiation Form PIF Approved 08/06/2019
    Project Initiation Form PRC Submitted 08/13/2019
    Project Initiation Form PRC Submitted 09/21/2020
    Project Review Committee PRC Tabled 04/30/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 02/01/2023
    100% Design 100% Package Comments to DE 04/04/2023
    25% Design 25% Package Received 06/21/2022
    25% Design 25% Package Comments to DE 08/22/2022
    25% Design Design Public Hearing 12/01/2022
    75% Design 75% Package Received 02/01/2023
    Final Design PS&E Received 06/22/2023
    Final Design PS&E Received - Resub 1 08/01/2023