Project Description: |
BOURNE- ROTARY IMPROVEMENTS
Work on this project consists of improving the traffic operations through restriping the rotary to 2 lanes and adding a channelized right turn lane from Route 28 northbound to Sandwich Road eastbound.
|
Location: |
|
Construction Begins: | Autumn 2023 |
Resident Engineer: | Neal Noversa![]() |
Construction Bid Price: | $1,769,622.60 |
District: | District 5 |
Current Status: | Construction and traffic punch list work has been completed. The project is currently in full beneficial use. Materials documentation being finalized in order to generate Materials Certificate. Scheduled work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 05/13/2025) |
|
Bridges |
|
|
|
|