Project Description:
REVERE- MALDEN- IMPROVEMENTS AT ROUTE 1 (NB) (PHASE 1)
The purpose of this project is to add-a-lane on Route 1 north bound between Copeland Circle and Salem Street offramp to improve the traffic operations and safety at this bottleneck.
Location:
  • City of Malden
  • City of Revere
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2029
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $7,120,000.00
    Estimated Total Federal Participating Construction Cost: $7,210,000.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 12/09/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MALDEN
    REVERE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $6,690,880.00
    State Cost: $1,672,720.00
    Total Cost: $8,363,600.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/13/2019
    Project Need Form PNF Approved 08/06/2019
    Project Initiation Form PIF Entered 08/13/2019
    Project Initiation Form PIF Approved 08/06/2019
    Project Initiation Form PRC Submitted 08/13/2019
    Project Review Committee PRC Approved 08/15/2019
    Project Management
    Consultant Contract Process NTP Issued 12/09/2022