Project Description:
NORTH ADAMS- BRAYTON ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
Installing and repairing 1000 linear feet of sidewalk will improve access connectivity safety and create the appropriate infrastructure for students walking and biking. Enhance pedestrian access and ADA compliance by striping existing and new crosswalks. Installation of new sidewalks and new grade of the public way will greatly improve the safety of students walking to school providing the appropriate infrastructure for pedestrians so they are not walking in the road with vehicles. The improvements will enhance visibility and connectivity for the students walking to and from school and accessing the amenities around the school. New sidewalks will provide access from a 100 unit low-income housing development to a park the school YMCA and adjoining neighborhoods.
Location:
  • City of North Adams
  • Construction Begins: Autumn 2022
    Resident Engineer: Peter Lamarre
    Construction Bid Price: $842,115.00
    District: District 1

    Contracts (1) Progress
    # 120082 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Sections of Brickyard Court and Brayton Hill Terrace at Route 2 (Mohawk Trail) (Safe Routes to School – Brayt Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/03/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/28/2019
    Project Need Form PNF Approved 07/30/2019
    Project Initiation Form PIF Entered 08/28/2019
    Project Initiation Form PIF Approved 08/27/2019
    Project Initiation Form PRC Submitted 08/30/2019
    Project Review Committee PRC Approved 09/18/2019
    Project Status Advertised 08/27/2022
    Project Management
    100% Design 100% Package Received 10/12/2021
    25% Design 25% Package Received 11/03/2020
    75% Design 75% Package Received 10/12/2021
    Final Design PS&E Received 04/01/2022
    Final Design PS&E Received - Resub 1 07/15/2022