Project Description:
MARLBOROUGH- HUDSON- RAMP IMPROVEMENTS AND RELATED WORK AT I-495 (SB) TO I-290 (WB)
The proposed improvements include widening the ramp to two lanes and improvements to the ramp alignment. Additional improvements involve minor widening of I-495 to create an exit only lane and a shared through/exit lane as well as widening on I-290 to accommodate the additional ramp lane. The deceleration lane will also be extended primarily through pavement markings. The work will entail resurfacing The I-495 SB and I-290 WB mainline barrels within the project limits to facilitate the changes to the pavement markings. Related work includes associated signage, minor drainage modifications and upgraded guardrail as needed.
Location:
  • Town of Hudson
  • City of Marlborough
  • Construction Begins: Autumn 2022
    Resident Engineer: Jonathan Viner
    Construction Bid Price: $5,473,226.65
    District: District 3

    Contracts (2) Progress
    # 119545 -- Construction Contract
    Roadway Reconstruction and Related Work I-495 (SB) Exit 25B Off-Ramp Completed
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/30/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/17/2019
    Project Initiation Form PIF Entered 09/17/2019
    Project Initiation Form PRC Submitted 09/18/2019
    Project Review Committee PRC Approved 10/11/2019
    Project Status Advertised 07/30/2022
    Project Management
    25% Design 25% Package Received 11/18/2019
    25% Design Design Public Hearing 02/25/2020
    75% Design 75% Package Received 03/25/2020
    75% Design 75% Package Comments to DE 05/27/2020
    Final Design PS&E Received 06/29/2020
    Final Design PS&E Received - Resub 1 01/25/2022