Project Description:
WAREHAM- CORRIDOR IMPROVEMENTS ON ROUTE 6 AT SWIFTS BEACH ROAD
The intent of this project is to improve bicycle and pedestrian accommodation along this section of the Route 6 corridor as well as provide a left turn lane as the Route 6/Swifts Beach Road intersection. Work on this project consists of pavement milling/overlay, traffic signal upgrades and installation, reconstructed sidewalks, ADA compliant curb ramps and associated roadway geometry.
Location:
  • Town of Wareham
  • Construction Begins: Spring 2026
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $6,824,300.00
    District: District 5
    Current Status: The contractor is anticipated to begin mobilizing equipment to the project site in the coming weeks. Initial construction activities will include the installation of advance warning signage, implementation of erosion control measures, tree trimming, and installation of tree protection. Utility companies are also expected to mobilize to the site to begin installation of new utility poles. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 09/29/2026)

    Contracts (3) Progress
    # 133932 -- Construction Contract
    Corridor Improvements on Route 6 at Swifts Beach Road
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86792 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/04/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/27/2019
    Project Initiation Form PIF Entered 09/27/2019
    Project Initiation Form PRC Submitted 09/27/2019
    Project Review Committee PRC Approved 10/19/2019
    Project Status Advertised 03/28/2026
    Project Management
    100% Design 100% Package Received 12/04/2024
    100% Design 100% Package Comments to DE 01/31/2025
    25% Design 25% Package Received 02/03/2022
    25% Design 25% Package Comments to DE 05/09/2022
    25% Design 25% Package Received - Resub 1 08/08/2022
    25% Design Design Public Hearing 06/21/2023
    75% Design 75% Package Received 07/25/2023
    75% Design 75% Package Comments to DE 10/05/2023
    Final Design PS&E Received 04/14/2025
    Final Design PS&E to FAPRO 03/09/2026
    Final Design PS&E Received - Resub 1 01/16/2026
    Final Design PS&E Received - Resub 2 02/20/2026