Project Description:
AGAWAM- ROBINSON PARK ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
This Safe Routes to School project will improve safety for students and residents who walk and bike in the Maple Street corridor from O'Brien's corner intersection to Walnut Street. A shared use path is proposed along the north side of Maple Street. Three Rapid Flash Beacon crossings are proposed at several locations along the corridor. ADA compliant curb cuts will be constructed as needed. A raised intersection with 3-way stop control is proposed at the intersection of Bridge and Maple Streets. The proposed cross section varies along the corridor. The shared use path will be 10' wide when possible and 8' wide in constricted areas. The treebelt will be maximized to provide a buffer between pedestrians and bicyclists in order to increase comfort and safety.
Location:
  • City of Agawam
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2024/2025
    Project Manager: Daniel Wilk
    Estimated Total Contract Cost: $3,919,483.10
    Estimated Total Federal Participating Construction Cost: $3,770,362.16
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 09/14/2024 )

    Contracts (1) Progress
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: AGAWAM
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • TAP increased from $1,448,972.00 to $3,544,068 via STIP Action #1. CRRS removed via STIP Action #1.
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $2,835,254.40
    State Cost: $708,813.60
    Total Cost: $3,544,068.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/25/2019
    Project Need Form PNF Approved 06/28/2019
    Project Initiation Form PIF Entered 10/25/2019
    Project Initiation Form PIF Approved 10/25/2019
    Project Initiation Form PRC Submitted 10/31/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Status Advertised 09/14/2024
    Project Management
    100% Design 100% Package Received 11/23/2022
    100% Design 100% Package Comments to DE 01/24/2023
    25% Design 25% Package Received 08/20/2021
    25% Design 25% Package Received 08/20/2021
    25% Design 25% Package Comments to DE 10/22/2021
    25% Design Design Public Hearing 05/19/2022
    75% Design 75% Package Received 11/23/2022
    Final Design PS&E Received 02/20/2024
    Final Design PS&E to FAPRO 08/28/2024