Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MONTAGUE- INTERSECTION IMPROVEMENTS AT ROUTE 63 AND NORTH LEVERETT ROAD
This project is intended to improve safety at the Route 63 and Route 47/North Leverett Road intersection. MassDOT was asked by the selectboard of Montague to look into this stop-controlled intersection due to numerous accidents due primarily to very poor sight lines. This project will improve the approaching roadway geometry and sight distance. Exact geometric configuration has not been decided, but includes the possibility of realigning the west side of North Leverett Road further to the south to line up with the east end, a possible roundabout, possible lowering of the roadway profile, and modifications to the adjacent bridge; alternatives to be discussed with designer.
Location:
  • Town of Montague
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2028
    Project Manager: Adetoyin Ayoola Olaoye
    Estimated Total Contract Cost: $2,792,000.00
    Estimated Total Federal Participating Construction Cost: $3,031,500.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 05/17/2023 )

    Contracts (1) Progress
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: MONTAGUE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • MPO Project (TEC) Score 37/100.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,164,886.00
    State Cost: $351,654.00
    Total Cost: $3,516,540.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2019
    Project Need Form PNF Approved 10/31/2019
    Project Initiation Form PIF Entered 11/05/2019
    Project Initiation Form PIF Approved 11/05/2019
    Project Initiation Form PRC Submitted 11/05/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    Consultant Contract Process NTP Issued 05/17/2023