Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STERLING- STORMWATER DRAINAGE IMPROVEMENTS AT WACHUSETT RESERVOIR ON ROUTE 110 (METROPOLITAN ROAD)
The proposed project will eliminate sources of direct stormwater discharge and potential hazardous materials releases from Route 110 to the Wachusett Reservoir, a public water supply to over three million users. The existing drainage from the roadway is typical of rural country drainage. The north side of the roadway sheet flows directly to a wetland and a small body of water. There is a cross culvert connecting the wetland to the reservoir to the south. The south side of the roadway sheet flows directly to the reservoir. The intent of the preliminary design is to drain the entire roadway to the existing wetland to the north. The existing cross culvert between the wetland and the reservoir will be eliminated. A new 550 foot diversion pipe is proposed to carry stormwater from the wetland to the body of water to the north, which is off of the reservoir's watershed land. A Hot Mix Asphalt Type "A" Modified berm will be constructed along the side of the road closest to the reservoir's edge. Due to how longitudinally flat the roadway is in this area, three catch basins will be installed in addition to the super-elevation.
Location:
  • Town of Sterling
  • Design Responsibility: Other
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $2,404,027.84
    Estimated Total Federal Participating Construction Cost: $2,598,292.19
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received - Resub 2 (as of 10/21/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: STERLING
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation (PROTECT)
    Federal Cost: $1,684,104.80
    State Cost: $421,026.20
    Total Cost: $2,105,131.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/12/2019
    Project Need Form PNF Approved 10/23/2019
    Project Initiation Form PIF Entered 11/12/2019
    Project Initiation Form PIF Approved 11/12/2019
    Project Initiation Form PRC Submitted 12/10/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    100% Design 100% Package Received 03/12/2024
    25% Design 25% Package Received 04/02/2021
    25% Design 25% Package Received - Resub 1 08/06/2021
    75% Design 75% Package Received 07/19/2023
    75% Design 75% Package Comments to DE 10/13/2023
    Final Design PS&E Received 03/12/2024
    Final Design PS&E Received - Resub 1 07/01/2024
    Final Design PS&E Received - Resub 2 10/21/2024