Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SUDBURY- WAYLAND- MASS CENTRAL RAIL TRAIL (MCRT)
The Massachusetts Department of Conservation and Recreation (DCR) is proposing a 1.9 mile segment of the MassCentral Rail Trail MCRT in Wayland and Sudbury. The project stretches from the Eversource Substation just east of Landham Road in Sudbury to Route 20 in Wayland near Russells Garden Center.
Location:
  • Town of Sudbury
  • Town of Wayland
  • Design Responsibility: Other
    Right of Way Responsibility: Other
    Construction Begins: Spring 2027
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $3,337,275.00
    Estimated Total Federal Participating Construction Cost: $3,626,262.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Approved (as of 11/11/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: SUDBURY
    WAYLAND
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $4,061,413 (CMAQ)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $3,249,130.40
    State Cost: $812,282.60
    Total Cost: $4,061,413.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/12/2019
    Project Need Form PNF Approved 10/23/2019
    Project Initiation Form PIF Entered 11/12/2019
    Project Initiation Form PIF Approved 11/12/2019
    Project Initiation Form PRC Submitted 12/10/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    25% Design 25% Package Received 04/26/2022
    25% Design 25% Package Comments to DE 07/26/2022
    25% Design 25% Package Approved 11/11/2022