Project Description:
STONEHAM- INTERSECTION IMPROVEMENTS AT ROUTE 28 (MAIN STREET), NORTH BORDER ROAD AND SOUTH STREET
The intent of the project is to improve safety at the Main Street intersections by updating the signal control system and lane assignments, and provide safe multimodal connections within the area. The project limits extend along: Main Street, between Cradock Bridge to the north and Thomas Street to the south; Mystic Avenue, between Main Street and Union Street; South Street, from Main Street and continuing westerly approximately 350 feet; and the Route 16 on and off-ramps.
Location:
  • Town of Stoneham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2028
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $5,657,219.40
    Estimated Total Federal Participating Construction Cost: $6,128,571.80
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Received (as of 01/24/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: STONEHAM
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,384,800.90
    State Cost: $487,200.10
    Total Cost: $4,872,001.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/22/2019
    Project Need Form PNF Approved 11/22/2019
    Project Initiation Form PIF Entered 11/22/2019
    Project Initiation Form PIF Approved 11/22/2019
    Project Initiation Form PRC Submitted 11/22/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    25% Design 25% Package Received 01/24/2025
    Consultant Contract Process NTP Issued 10/12/2022