Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DARTMOUTH- CROSS ROAD CORRIDOR IMPROVEMENTS
The Town of Dartmouth intends to rehabilitate Cross Road from the Fire Station to the Autumn Glen Senior Living Center, approximately 2,400 ft. The Town intends to provide 11 foot travel lanes 5 foot shoulders and 6 foot wide sidewalks both sides to the maximum extent practicable. The Town intends to provide vertical curbing and a closed drainage system and incorporate stormwater Best Management Practices to the maximum extent practicable. The Town will evaluate turn lanes and crosswalks at the George H Potter Elementary School, North Dartmouth Library, Saint George Greek Orthodox Church and Autumn Glen Senior Living Center.
Location:
  • Town of Dartmouth
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Filbert Yee
    Estimated Total Federal Participating Construction Cost: $5,788,315.10
    District: District 5
    Current Status: 25% Package Received (as of 02/21/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/25/2019
    Project Need Form PNF Approved 06/20/2019
    Project Initiation Form PIF Entered 11/25/2019
    Project Initiation Form PIF Approved 11/25/2019
    Project Initiation Form PRC Submitted 11/25/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    25% Design 25% Package Received 02/21/2023