HARWICH- HARWICH ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
Location:
  • Town of Harwich
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2025/2026
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $3,160,789.63
    Estimated Total Federal Participating Construction Cost: $3,657,019.82
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: PS&E Received (as of 04/03/2025 )

    Contracts (1) Progress
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: HARWICH
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC - $2,417,460; TAP; GHG analysis to be completed when all required inputs are available
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,933,968.00
    State Cost: $483,492.00
    Total Cost: $2,417,460.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/26/2019
    Project Need Form PNF Approved 11/25/2019
    Project Initiation Form PIF Entered 11/26/2019
    Project Initiation Form PIF Approved 11/26/2019
    Project Initiation Form PRC Submitted 11/26/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    100% Design 100% Package Received 12/09/2024
    100% Design 100% Package Received - Resub 1 01/14/2025
    25% Design 25% Package Received 12/06/2022
    25% Design 25% Package Comments to DE 01/06/2023
    25% Design 25% Package Received - Resub 1 01/26/2024
    25% Design Design Public Hearing 06/12/2024
    75% Design 75% Package Received 12/09/2024
    Final Design PS&E Received 04/03/2025