Project Description:
GARDNER- ELM STREET RESURFACING AND SIDEWALK IMPROVEMENTS (SRTS)
The Elm Street Corridor between Temple Street and Cross Street in the vicinity of Elm Street Elementary School will be full improved for vehicle, pedestrian, and bicycle safety and accessibility to improve multi-modal transportation under the SRTS Infrastructure Program. The work will include mill and pave of the roadway, new and/or reset granite curbing, concrete sidewalks, curb extensions, raised crossings, Rapid Rectangular Flashing Beacons, and new signs and pavement markings.
Location:
  • City of Gardner
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: David Shedd
    Estimated Total Contract Cost: $1,899,589.88
    Estimated Total Federal Participating Construction Cost: $2,162,272.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received (as of 05/23/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: GARDNER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,588,110.40
    State Cost: $397,027.60
    Total Cost: $1,985,138.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/02/2019
    Project Need Form PNF Approved 11/20/2019
    Project Initiation Form PIF Entered 12/02/2019
    Project Initiation Form PIF Approved 12/02/2019
    Project Initiation Form PRC Submitted 12/10/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    100% Design 100% Package Received 09/26/2022
    100% Design 100% Package Comments to DE 10/28/2022
    25% Design 25% Package Received 03/05/2021
    25% Design 25% Package Comments to DE 05/17/2021
    Final Design PS&E Received 05/23/2023