Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOURNE- BOURNE RAIL TRAIL (PHASE 2)
The Bourne Rail Trail Phase II project is a proposed 2-mile multi-use path extending from the terminus of the future Bourne Rail Trail Phase I at Monument Neck Road to the north to Monk's Park at Valley Bars Road to the south. The Bourne Rail Trail is a rail-with-trail type path, running alongside the existing railroad tracks in Bourne. Separation between the trail and the existing tracks is crucial to the project for safety purposes, as well as the improvement of raised and at-grade crossings for safe access for bicyclists and pedestrians. The existing rail line has a above water crossing at Back River and an above road crossing at Emmons Road and Valley Bars Circle (the proposed end of the Phase II section). There is also one bridge crossing over the rail line at Briarwood Lane.The bridge crossing over Emmons Road could be converted to an at grade crossing for the rail trail if significant filling were to take place, otherwise a rail trail bridge would be needed at this location parallel to the existing train bridge. The rail trail Phase II would terminate at Valley Bars Circle, so the rail trail would end at grade with the roadway for users to access the road. There are also 4 at grade crossings throughout the proposes rail trail corridor. Crossing are located at the Lobster Trap access road/residential access road (unnamed), Evergreen Hill Road, Worcester Avenue, and the emergency beach access road at Monument Beach.
Location:
  • Town of Bourne
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $7,040,000.00
    Estimated Total Federal Participating Construction Cost: $7,610,000.00
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/04/2019
    Project Need Form PNF Approved 11/08/2019
    Project Initiation Form PIF Entered 12/04/2019
    Project Initiation Form PIF Approved 12/04/2019
    Project Initiation Form PRC Submitted 12/04/2019
    Project Review Committee PRC Approved 12/23/2019
    Project Management