Project Description:
CHELSEA- RECONSTRUCTION OF SPRUCE STREET, FROM EVERETT AVENUE TO WILLIAMS STREET
The primary objective of this project is the creation of a vibrant, accessible, and safe corridor in order to stimulate the Shopping Center and adjacent industrial area, support the Critical Urban Freight Corridor, and to increase access of patrons to its business, commercial, and residential areas. Through the comprehensive rehabilitation of this roadway, we will address non-compliance with ADA standards, implement upgraded signalization at intersections, reduce congestion and optimize circulation, reduce all crash types, and introduce adequate bicycle and pedestrian facilities to promote mobility.
Location:
  • City of Chelsea
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2026
    Project Manager: Alolade O Campbell
    Estimated Total Contract Cost: $5,640,500.00
    Estimated Total Federal Participating Construction Cost: $6,220,475.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CHELSEA
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $5,841,153 (HSIP)
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $5,257,037.70
    State Cost: $584,115.30
    Total Cost: $5,841,153.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/05/2019
    Project Need Form PNF Approved 03/05/2018
    Project Initiation Form PIF Entered 12/05/2019
    Project Initiation Form PIF Approved 12/05/2019
    Project Initiation Form PRC Submitted 12/13/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management