Project Description: |
WRENTHAM- INTERSECTION IMPROVEMENTS ON ROUTE 1A AT NORTH AND WINTER STREET
The proposed project will address faulty lines of sight at all approaches to the intersection by including alternatives to the existing 2-way flashing post-mounted beacon at the intersection, which excludes Rte. 1A (Dedham St.), and providing adequate signage and pavement markings.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2028 |
Project Manager: | Jonathan E Freeman![]() |
Estimated Total Contract Cost: | $5,681,439.50 |
Estimated Total Federal Participating Construction Cost: | $2,649,000.00 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | 25% Package Received (as of 08/23/2024 ) |
|