Project Description:
NATICK- LAKE COCHITUATE PATH
MassDOT and the town of Natick are proposing an approximate 0.4 mile segment of shared-used path along Route 9. The project limits are from Archer Drive to the Cochituate Rail Trail. No roadway crossings are proposed and the shared-use path will provide a critical connection to the Cochituate Rail Trail. Some vegetation removal grading and replacement fencing along properties may be required.
Location:
  • Town of Natick
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: David Shedd
    Estimated Total Contract Cost: $4,524,078.80
    Estimated Total Federal Participating Construction Cost: $5,092,449.60
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: 75% Package Received (as of 04/16/2024 )

    Contracts (1) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NATICK
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,742,684.00
    State Cost: $685,671.00
    Total Cost: $3,428,355.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/17/2019
    Project Need Form PNF Approved 12/17/2019
    Project Initiation Form PIF Entered 12/17/2019
    Project Initiation Form PIF Approved 12/17/2019
    Project Initiation Form PRC Submitted 12/17/2019
    Project Review Committee PRC Approved 12/19/2019
    Project Management
    25% Design 25% Package Received 05/03/2021
    75% Design 75% Package Received 04/16/2024
    Consultant Contract Process NTP Issued 06/10/2020