Project Description:
CLINTON- RECONSTRUCTION OF STERLING STREET (ROUTE 62), FROM WILLOW/LAWRENCE STREET TO MAIN STREET
This project will include roadway reconstruction along Sterling Street from the intersection with Willow/Lawrence Street to just west of Main Street in Clinton, MA. Due to the severely deteriorated roadway condition, full depth reconstruction is anticipated. The proposed cross section will consist of two 11-foot travel lanes, 5-foot shoulders/bike lanes on both sides, and 5.5-foot sidewalks on both sides. Installation of new curbing along the corridor is anticipated as existing curbing is worn with little reveal. Existing sidewalks are either lacking on one side of the road or severely deteriorated, therefore new sidewalk on both sides will be proposed. New signs and pavement markings will be proposed to meet the latest MUTCD requirements. Improvements to the drainage infrastructure is anticipated as the roadway profile is generally very flat; therefore, additional catch basins will be added along the corridor. Reconstruction of short retaining walls less than 4 feet tall are anticipated. New curb-cut ramps will be proposed along the corridor as there are none that meet ADA/AAB requirements today.
Location:
  • Town of Clinton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $4,373,678.50
    Estimated Total Federal Participating Construction Cost: $4,919,042.50
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Received - Resub 1 (as of 06/13/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: CLINTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,250,052.80
    State Cost: $1,062,513.20
    Total Cost: $5,312,566.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/20/2019
    Project Need Form PNF Approved 12/09/2019
    Project Initiation Form PIF Entered 12/20/2019
    Project Initiation Form PIF Approved 12/20/2019
    Project Initiation Form PRC Submitted 04/27/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Management
    25% Design 25% Package Received 11/03/2021
    25% Design 25% Package Comments to DE 02/03/2022
    25% Design 25% Package Received - Resub 1 06/13/2023