Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- DRAWBRIDGE OPERATION, REPAIR & SYSTEMATIC PRESERVATION AT VARIOUS LOCATIONS (INCLUDING MARTH'S VINEYARD)
Location:
Construction Begins: Winter 2020/2021
Resident Engineer: Louis daPonte
Construction Bid Price: $2,897,126.00
District: District 5

Contracts (1) Progress
# 113342 -- Construction Contract
Scheduled and Emergency Drawbridge Operation, Maintenance and Repairs at Various Locations (Including Martha’s Vineyard) Completed

Bridges

Contract Dates
Notice to Proceed: 01/08/2021
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 12/31/2019
Project Initiation Form PIF Entered 12/31/2019
Project Initiation Form PRC Submitted 12/31/2019
Project Review Committee PRC Approved 01/06/2020
Project Status Advertised 10/24/2020
Project Management
100% Design 100% Package Received 06/04/2020
100% Design 100% Package Comments to DE 07/02/2020
Final Design PS&E Received 07/17/2020
Final Design PS&E Received - Resub 1 08/04/2020