Project Description:
BARNSTABLE- SYSTEMATIC BRIDGE PRESERVATION, B-01-011 (49T) AND B-01-016 (49R), ROUTE 149 (MEETING HOUSE WAY) OVER ROUTE 6 MID-CAPE HIGHWAY
This contract shall consist of repairs and maintenance of bridge B-01-011 (49T) Route 149 Meeting House Way over Route 6 Mid-Cape Highway in Barnstable
Location:
  • Town of Barnstable
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: M. Ali Jalinous
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: PS&E Received - Resub 3 (as of 12/21/2020 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status PIF Entered 12/31/2019
    Project Status PNF Entered 12/31/2019
    Project Status PRC Approved 01/08/2020
    Project Status PRC Submitted 12/31/2019
    Project Management
    Consultant Contract Process 100% Package Received 09/08/2020
    Consultant Contract Process PS&E Received 10/09/2020
    Consultant Contract Process 100% Package Comments to DE 09/30/2020
    Consultant Contract Process PS&E Received - Resub 1 11/27/2020
    Consultant Contract Process PS&E Received - Resub 2 12/14/2020
    Consultant Contract Process PS&E Received - Resub 3 12/21/2020