FALL RIVER- SYSTEMATIC BRIDGE PRESERVATION, F-02-050 (3VD), ROUTE 79 (NB) OVER ROUTE 24 (SB)
Location:
  • City of Fall River
  • Construction Begins: Spring 2021
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $794,100.00
    District: District 5
    Current Status: The contractor has been installing the containment system which will be used for cleaning operations. This project currently sits within the project limits of an active paving contract, and the Contractor has temporarily suspended operations to allow for the completion of paving operations on Route 24. Scheduled work hours are Sunday through Friday 8:00 PM to 5:00 AM. (as of 09/09/2021)

    Contracts (1) Progress
    # 114042 -- Construction Contract
    Bridge Cleaning, Painting, and Related Work (Including Structural Steel Repairs) Br. No. F-02-050 Route 79 (North) over Route 24 (South) 34% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/29/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/31/2019
    Project Initiation Form PIF Entered 12/31/2019
    Project Initiation Form PRC Submitted 12/31/2019
    Project Review Committee PRC Approved 01/08/2020
    Project Status Advertised 02/20/2021
    Project Management
    100% Design 100% Package Received 11/19/2020
    100% Design 100% Package Comments to DE 12/16/2020
    Final Design PS&E Received 12/28/2020
    Final Design PS&E Received - Resub 1 01/13/2021