Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- SCHEDULED & EMERGENCY BRIDGE DECK & JOINT REPAIRS AT VARIOUS LOCATIONS
Location:
Construction Begins: Spring 2021
Resident Engineer: Scott Borges
Construction Bid Price: $1,250,163.00
District: District 5

Contracts (1) Progress
# 114377 -- Construction Contract
Scheduled and Emergency Bridge Deck and Joint Repairs at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/18/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/31/2019
    Project Initiation Form PIF Entered 12/31/2019
    Project Initiation Form PRC Submitted 12/31/2019
    Project Review Committee PRC Approved 01/06/2020
    Project Status Advertised 04/17/2021
    Project Management
    100% Design 100% Package Received 12/29/2020
    100% Design 100% Package Comments to DE 02/02/2021
    Final Design PS&E Received 02/18/2021
    Final Design PS&E Received - Resub 1 03/17/2021
    Final Design PS&E Received - Resub 2 03/31/2021
    Final Design PS&E Received - Resub 3 04/07/2021