Project Description:
FALL RIVER- HIGHWAY LIGHTING UPGRADES ON I-195 UNDER CITY HALL PLAZA
Location:
  • City of Fall River
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $13,295,189.06
    Estimated Total Federal Participating Construction Cost: $13,703,016.29
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 100% Package Comments to DE (as of 09/09/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: FALL RIVER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $12,057,048.80
    State Cost: $3,014,262.20
    Total Cost: $15,071,311.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2020
    Project Initiation Form PIF Entered 02/04/2020
    Project Initiation Form PRC Submitted 02/04/2020
    Project Review Committee PRC Approved 02/11/2020
    Project Management
    100% Design 100% Package Received 08/02/2026
    100% Design 100% Package Comments to DE 09/09/2026
    25% Design 25% Package Received 02/12/2025
    75% Design 75% Package Received 12/01/2025