Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 1- DISTRICT 2- DISTRICT 3- DISTRICT 6- CONVERSION OF INTERSTATE AND FREEWAY EXIT SIGNS TO MILEPOST-BASED NUMBERING ON THE MASSACHUSETTS TURNPIKE (I-90)
Location:
Construction Begins: Summer 2020
Resident Engineer: Adam Nabulsi
Construction Bid Price: $150,588.80
District: District 3

Contracts (1) Progress
# 111439 -- Construction Contract
Conversion of Interstate and Freeway Exit Signs to Milepost-Based Numbering on the Massachusetts Turnpike (I-90) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/25/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2020
    Project Initiation Form PIF Entered 02/04/2020
    Project Initiation Form PRC Submitted 02/04/2020
    Project Review Committee PRC Approved 02/10/2020
    Project Status Advertised 05/30/2020
    Project Management
    100% Design 100% Package Received 02/19/2020
    75% Design 75% Package Received 02/19/2020
    Final Design PS&E Received 04/09/2020
    Final Design PS&E to FAPRO 05/15/2020