Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CONCORD- BRIDGE REHABILITATION, C-19-021 (2DT), ROUTE 2 OVER SUDBURY RIVER
The proposed rehabilitation work will include an expanded preservation scheme wherein the existing bridge parapet will be reconstructed with a CT-TL2 barrier, with an architectural treatment, secured to a moment slab. The intent of the architectural treatment is to replicate the look of the existing stone work on the spandrel wall. Modified guardrail transitions will be incorporated at each corner of the bridge. The approach guardrail will be replaced for 50 feet at each corner of the bridge and the existing median barrier will remain.
Location:
  • Town of Concord
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $1,275,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2020
    Project Initiation Form PIF Entered 02/24/2020
    Project Initiation Form PRC Submitted 02/26/2020
    Project Review Committee PRC Approved 03/24/2020
    Project Management