Project Description:
NEW BEDFORD TO TAUNTON- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 140
This project will replace and update the existing guide and traffic signs on Route 140 between the Phillips Street/Church Street interchange in New Bedford and the Stevens Street/County Street interchange in Taunton with new signs mounted on existing supports, including applicable signs on intersecting secondary roadways.
Location:
  • Town of Lakeville
  • City of New Bedford
  • City of Taunton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $1,184,330.00
    Estimated Total Federal Participating Construction Cost: $1,320,211.25
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received (as of 10/25/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: LAKEVILLE
    NEW BEDFORD
    TAUNTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $802,845.00
    State Cost: $89,205.00
    Total Cost: $892,050.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2020
    Project Initiation Form PIF Entered 03/05/2020
    Project Initiation Form PRC Submitted 03/05/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Management
    25% Design 25% Package Received 10/25/2024
    Consultant Contract Process NTP Issued 08/07/2024