Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WILLIAMSTOWN- INTERSECTION IMPROVEMENTS AT ROUTE 7 AND ROUTE 43
The proposed project consists of constructing a roundabout at the intersection of Route 7 and Route 43 to improve safety and operations. Pedestrian connections between The Store at Five Corners and Bloedel Park will be improved with a new marked crosswalk and accessible ramps to cross the south leg of Route 7. Landscaping enhancements are proposed to create a welcoming gateway to Williamstown.
Location:
  • Town of Williamstown
  • Construction Begins: Autumn 2023
    Resident Engineer: John Bedard
    Construction Bid Price: $3,799,274.02
    District: District 1

    Contracts (1) Progress
    # 123877 -- Construction Contract
    Intersection Improvements at Route 7 and Route 43 23% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/11/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2020
    Project Need Form PNF Approved 03/05/2020
    Project Initiation Form PIF Entered 03/05/2020
    Project Initiation Form PIF Approved 03/05/2020
    Project Initiation Form PRC Submitted 04/22/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 05/19/2023
    25% Design 25% Package Received 11/12/2021
    25% Design 25% Package Comments to DE 12/14/2021
    25% Design Design Public Hearing 06/21/2022
    75% Design 75% Package Received 01/06/2023
    75% Design 75% Package Comments to DE 03/06/2023
    Final Design PS&E Received 05/19/2023
    Final Design PS&E Received - Resub 1 08/04/2023
    Consultant Contract Process NTP Issued 12/23/2020