Project Description:
UXBRIDGE TO WORCESTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 146
This project will replace and update the guide and traffic signs on Route 146 between Uxbridge and Worcester with new signs mounted on new sign supports, including applicable signs on intersecting secondary roadways
Location:
  • Town of Douglas
  • Town of Millbury
  • Town of Northbridge
  • Town of Sutton
  • Town of Uxbridge
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $6,954,482.00
    Estimated Total Federal Participating Construction Cost: $7,214,103.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: 100% Package Comments to DE (as of 09/30/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DOUGLAS
    MILLBURY
    NORTHBRIDGE
    SUTTON
    UXBRIDGE
    WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $7,081,899, Design Status = 25%
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $6,373,709.10
    State Cost: $708,189.90
    Total Cost: $7,081,899.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2020
    Project Initiation Form PIF Entered 03/05/2020
    Project Initiation Form PRC Submitted 03/05/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Management
    100% Design 100% Package Received 07/29/2024
    100% Design 100% Package Comments to DE 09/30/2024
    25% Design 25% Package Received 12/08/2023
    75% Design 75% Package Received 07/29/2024