Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BURLINGTON TO TYNGSBOROUGH- PAVEMENT PRESERVATION ON ROUTE 3
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Burlington
  • Town of Chelmsford
  • Town of Lexington
  • City of Lowell
  • Town of Tyngsborough
  • Town of Westford
  • Construction Begins: Summer 2025
    Resident Engineer: Christopher Sacca
    Construction Bid Price: $17,676,110.60
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the STATEWIDE.
    District: District 4

    Contracts (1) Progress
    # 129715 -- Construction Contract
    Pavement Preservation on Route 3

    Bridges

    Contract Dates
    Notice to Proceed: 08/07/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: BEDFORD
    BILLERICA
    BURLINGTON
    CHELMSFORD
    LOWELL
    TYNGSBOROUGH
    WESTFORD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $18,964,671.20
    State Cost: $4,741,167.80
    Total Cost: $23,705,839.00
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $1,345,996.80
    State Cost: $336,499.20
    Total Cost: $1,682,496.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2020
    Project Initiation Form PIF Entered 03/06/2020
    Project Initiation Form PRC Submitted 03/06/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Status Advertised 03/15/2025
    Project Management
    100% Design 100% Package Received 12/13/2024
    100% Design 100% Package Received 12/30/2024
    25% Design 25% Package Received 09/05/2024
    25% Design 25% Package Comments to DE 10/08/2024
    75% Design 75% Package Received 09/05/2024
    75% Design 75% Package Comments to DE 10/08/2024
    Final Design PS&E Received 12/30/2024
    Final Design PS&E Received - Resub 1 02/26/2025