Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BURLINGTON TO TYNGSBOROUGH- PAVEMENT PRESERVATION ON ROUTE 3
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Burlington
  • Town of Chelmsford
  • Town of Lexington
  • City of Lowell
  • Town of Tyngsborough
  • Town of Westford
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Eric I Nova
    Estimated Total Contract Cost: $24,283,836.00
    Estimated Total Federal Participating Construction Cost: $24,628,863.45
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the STATEWIDE.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 03/15/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: BEDFORD
    BILLERICA
    BURLINGTON
    CHELMSFORD
    LOWELL
    TYNGSBOROUGH
    WESTFORD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $12,512,008.80
    State Cost: $3,128,002.20
    Total Cost: $15,640,011.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2020
    Project Initiation Form PIF Entered 03/06/2020
    Project Initiation Form PRC Submitted 03/06/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Status Advertised 03/15/2025
    Project Management
    100% Design 100% Package Received 12/13/2024
    100% Design 100% Package Received 12/30/2024
    25% Design 25% Package Received 09/05/2024
    25% Design 25% Package Comments to DE 10/08/2024
    75% Design 75% Package Received 09/05/2024
    75% Design 75% Package Comments to DE 10/08/2024
    Final Design PS&E Received 12/30/2024
    Final Design PS&E Received - Resub 1 02/26/2025