Project Description:
ACTON- BOXBOROUGH- LITTLETON- PAVEMENT PRESERVATION ON ROUTE 2
Location:
  • Town of Acton
  • Town of Boxborough
  • Town of Littleton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2024
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $7,061,139.37
    Estimated Total Federal Participating Construction Cost: $7,014,564.97
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 03/30/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: ACTON
    BOXBOROUGH
    LITTLETON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Moved to FF Y2024 and decreased from 7,867,299.00 to $7,547,749 via STIP Action 3.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $6,038,199.20
    State Cost: $1,509,549.80
    Total Cost: $7,547,749.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2020
    Project Need Form PNF Approved 03/06/2020
    Project Initiation Form PIF Entered 03/06/2020
    Project Initiation Form PIF Approved 03/06/2020
    Project Initiation Form PRC Submitted 03/06/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Status Advertised 03/30/2024
    Project Management
    100% Design 100% Package Received 12/06/2023
    25% Design 25% Package Received 10/02/2023
    75% Design 75% Package Received 10/02/2023
    75% Design 75% Package Comments to DE 11/02/2023
    Final Design PS&E Received 12/06/2023
    Final Design PS&E Received - Resub 1 01/16/2024