Project Description:
BOLTON- BOXBOROUGH- HARVARD- LITTLETON- PAVEMENT PRESERVATION ON I-495
This project consists of milling and placing a Ultra Thin Bonded Overlay on Interstate 495 in the towns of Berlin, Bolton, Boxborough, and Harvard. Additional work includes adjusting drainage structures, repairing guardrail, and new pavement markings. The project begins at the Berlin/Bolton town line (mm 67.6±). The project ends at the Boxborough/Littleton town line (mm 77.0±). The total length of this project is approximately 9.4 miles. The bridge work consists of full depth pavement removal, joint rehabilitation, full depth and/or partial depth deck repairs, and railing/parapet repairs. Joint rehabilitation work will be required for all bridge joints, and, in general, consists of slab-over backwall construction at all abutments and a pre-compressed seal joint at all piers. The locations of full and partial depth deck repairs will be as directed by the Engineer. There are also several locations where the existing bridge railing is either damaged, or missing, and requires replacement in-kind.
Location:
  • Town of Bolton
  • Town of Boxborough
  • Town of Harvard
  • Town of Littleton
  • Construction Begins: Spring 2021
    Resident Engineer: Steven Crain
    Construction Bid Price: $9,975,351.00
    District: District 3

    Contracts (1) Progress
    # 114111 -- Construction Contract
    Pavement Preservation and Related Work (Including 6 Bridges) along a Section of Interstate 495 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/08/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2020
    Project Need Form PNF Approved 03/06/2020
    Project Initiation Form PIF Entered 03/06/2020
    Project Initiation Form PIF Approved 03/06/2020
    Project Initiation Form PRC Submitted 03/06/2020
    Project Review Committee PRC Approved 03/09/2020
    Project Status Advertised 03/06/2021
    Project Management
    25% Design 25% Package Received 08/28/2020
    25% Design 25% Package Received 08/28/2020
    75% Design 75% Package Received 08/28/2020
    Final Design PS&E Received 11/24/2020
    Final Design PS&E to FAPRO 02/22/2021