Project Description:
CHELMSFORD- MEDFORD- SOMERVILLE- STONEHAM- INTERSTATE PRESERVATION ON I-93 & I-495
Location:
  • Town of Chelmsford
  • City of Medford
  • City of Somerville
  • Town of Stoneham
  • Construction Begins: Spring 2021
    Resident Engineer: Edward Conley
    Construction Bid Price: $5,798,305.38
    District: District 4
    Current Status: Permanent protective barrier has been installed along a section of I-93 at the Salem Street on ramp. Temporary protective barrier as been removed from the located noted where the permanent barrier was installed. Permanent concrete barrier installation will continue through September along the I-93 northbound corridor just before the Salem Street on-ramp. (as of 08/25/2022)

    Contracts (1) Progress
    # 113890 -- Construction Contract
    Resurfacing and Related Work on Sections of Interstates 495 and 93 69% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/13/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2020
    Project Need Form PNF Approved 03/06/2020
    Project Initiation Form PIF Entered 03/06/2020
    Project Initiation Form PIF Approved 03/06/2020
    Project Initiation Form PRC Submitted 03/06/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Status Advertised 01/23/2021
    Project Management
    100% Design 100% Package Received 10/01/2020
    100% Design 100% Package Comments to DE 11/03/2020
    Final Design PS&E Received 01/04/2021
    Final Design PS&E to FAPRO 01/04/2021