MEDFORD- READING- SOMERVILLE- STONEHAM- WINCHESTER- WOBURN- INTERSTATE PAVEMENT PRESERVATION ON I-93
Interstate Pavement Preservation on I93 from mile 20.7 to 29.2. The work under this Contract on Interstate 93 includes resurfacing of the mainline, selected bridges, selected ramps, and Salem Street Rotary from Shore Drive in Somerville to just north of the Reading/Woburn Town Line. These limits shall be fine milled to a depth of 2” and resurfaced with 2” of Superpave High RAP Surface Course. Related work includes upgrading existing guardrail within the project limits; reconstructing and constructing pedestrian curb ramps; adjusting, cleaning and rebuilding drainage structures; replacing frames, grates, and covers with lock down castings; removing and resetting granite curb, granite edging and replacing HMA berm as needed; installation of milling mulch beneath guardrail and at eroded shoulders, removing and resetting signs, median barrier repair, trimming vegetation within clear zones and site lines, replacing scored concrete pavement at gores with milled rumble strips, installing traffic counting stations, installing final pavement markings and slotted pavement markers, placing rumble strips, temporary traffic control, and other incidental items of work.
Location:
  • City of Medford
  • Town of Reading
  • City of Somerville
  • Town of Stoneham
  • Town of Winchester
  • City of Woburn
  • Construction Begins: Summer 2023
    Resident Engineer: Matthew Caputo
    Construction Bid Price: $36,122,640.00
    District: District 4
    Current Status: Construction activities will resume in the Spring 2024. (as of 11/20/2023)

    Contracts (1) Progress
    # 121698 -- Construction Contract
    Interstate Pavement Preservation on I-93 2% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 08/09/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Construction activities will resume in the Spring 2024.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2020
    Project Need Form PNF Approved 03/06/2020
    Project Initiation Form PIF Entered 03/06/2020
    Project Initiation Form PIF Approved 03/06/2020
    Project Initiation Form PRC Submitted 03/06/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Status Advertised 03/25/2023
    Project Management
    100% Design 100% Package Received 01/27/2023
    25% Design 25% Package Received 09/15/2022
    75% Design 75% Package Received 09/15/2022
    75% Design 75% Package Comments to DE 10/20/2022
    Final Design PS&E Received 03/10/2023
    Final Design PS&E to FAPRO 03/13/2023