Project Description: |
LEE- RESURFACING AND RELATED WORK ON ROUTE 20
The limits of this project are from MM 18.58 (just north of I-90 overpass at Exit 10) to MM 23.15
(Lee/Becket town-line). The project will acquire Right-of-Way at select locations between MM 18.58
and MM 20.28 for the purpose of establishing State Highway Layout. Resurfacing and related work on Route 20 will begin at MM 20.28 (just west of the bridge over Greenwater Brook) and end at the Lee/Becket line (MM 23.15).
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2025 |
Project Manager: | Anni H Autio![]() |
Estimated Total Contract Cost: | $5,346,010.00 |
Estimated Total Federal Participating Construction Cost: | $5,832,011.00 |
Funding Provision: | This project is planned to be funded through the 2024 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization. |
District: | District 1 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 03/01/2023 ) |
|
Bridges |
|
|
|