Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LEE- RESURFACING AND RELATED WORK ON ROUTE 20
The limits of this project are from MM 18.58 (just north of I-90 overpass at Exit 10) to MM 23.15 (Lee/Becket town-line). The project will acquire Right-of-Way at select locations between MM 18.58 and MM 20.28 for the purpose of establishing State Highway Layout. Resurfacing and related work on Route 20 will begin at MM 20.28 (just west of the bridge over Greenwater Brook) and end at the Lee/Becket line (MM 23.15).
Location:
  • Town of Lee
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $9,145,395.60
    Estimated Total Federal Participating Construction Cost: $9,429,736.98
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 75% Package Received (as of 06/17/2024 )

    Contracts (1) Progress
    # 115753 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,615,108.80
    State Cost: $1,403,777.20
    Total Cost: $7,018,886.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2020
    Project Need Form PNF Approved 03/09/2020
    Project Initiation Form PIF Entered 03/09/2020
    Project Initiation Form PIF Approved 03/09/2020
    Project Initiation Form PRC Submitted 03/09/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Management
    25% Design 25% Package Received 10/27/2023
    75% Design 75% Package Received 06/17/2024
    Consultant Contract Process NTP Issued 03/01/2023