LEE- RESURFACING AND RELATED WORK ON ROUTE 20
Location:
  • Town of Lee
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $6,689,645.34
    Estimated Total Federal Participating Construction Cost: $6,861,045.62
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: PS&E Received - Resub 1 (as of 02/13/2026 )

    Contracts (1) Progress
    # 115753 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • decreased from $9,422,966 via STIP Action 7.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,440,630.40
    State Cost: $1,360,157.60
    Total Cost: $6,800,788.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2020
    Project Need Form PNF Approved 03/09/2020
    Project Initiation Form PIF Entered 03/09/2020
    Project Initiation Form PIF Approved 03/09/2020
    Project Initiation Form PRC Submitted 03/09/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Management
    100% Design 100% Package Received 09/24/2025
    25% Design 25% Package Received 10/27/2023
    75% Design 75% Package Received 06/17/2024
    Final Design PS&E Received 12/02/2025
    Final Design PS&E Received - Resub 1 02/13/2026
    Consultant Contract Process NTP Issued 03/01/2023